What a JDI Kitchen Remodel Looks Like, Start to Finish
By the JDI Construction teamReviewed by Arthur Kulchitskiy, Project ConsultantUpdated October 20265 min read
At JDI Construction, the construction phase of a kitchen remodel typically takes about 3 weeks for a cosmetic refresh, about 5 weeks for a pull-and-replace in the same layout, and 5 to 8 weeks for a full gut. Design, selections, ordering and permits come first, and their length depends on your decisions and on lead times.
This page describes how a kitchen remodel runs at JDI Construction, from the first phone call to the final walkthrough: who you meet, what you decide, what happens in the kitchen and how long each part takes. The construction figures come from Arthur Kulchitskiy, JDI project consultant, as of October 2026. For a general picture of how any kitchen remodel is sequenced, see how long a kitchen remodel takes.
How long the construction phase takes
The time your kitchen is under construction depends mostly on the level of the remodel. These are JDI's typical figures for the construction phase:
| Remodel level | What it usually involves | Typical construction time at JDI |
|---|---|---|
| Cosmetic refresh | Cabinets and layout stay. New surfaces, finishes, fixtures in the same positions. | About 3 weeks |
| Pull-and-replace | New cabinets, countertops and appliances in the same layout. | About 5 weeks |
| Full gut | The room goes back to the studs. Plumbing, wiring or walls may move. | 5 to 8 weeks |
| Expansion or addition | The kitchen gains floor area. | Scheduled project by project |
Not sure which level your project is? The page on kitchen remodel levels sets out what each one includes. The figures above start when the work in your kitchen starts. Everything in the next section comes first.
Step 1: The first call and the in-home consultation
You reach out online or by phone and schedule a free consultation. A renovation specialist visits your home, listens to what you want the kitchen to do, and talks through your vision, budget, timeline, design ideas and goals. They measure and look at the things that limit a design: walls, the plumbing below the sink, the electrical panel and access from below or above.
Scheduling a bid also gets you 3D renderings of the proposed kitchen at no charge, so you can see the layout before you commit to anything. Our page on the free 3D kitchen design explains what you get and how to review it. Afterward you receive a written, line-item estimate. If you already have a design or work with your own designer, JDI can price that design and work with them.
Step 2: Design, selections and ordering
When you sign the design agreement, JDI's design team meets with you about priorities and style and develops the design with you. You can expect layout plans, design options, finish selections, 3D design renders and mood boards, and visits to partner showrooms to choose materials and fixtures in person.
Once every choice is made, the design is checked against the budget, materials are ordered and the construction phase is scheduled, including the permit process. This is the stage you control most. A kitchen whose cabinets, countertop material, sink, faucet, appliances, tile and lighting are all chosen before demolition is a kitchen that keeps to its schedule.
How long this stage takes depends on how quickly decisions are made and on current lead times, which is why JDI does not give one number for it. Ask for the expected delivery dates of your cabinets and any special-order items, since those set the start date.
Step 3: Permits
Most pull-and-replace and full-gut kitchens need permits, and JDI pulls the permits the work requires. In the City of Vancouver, Vancouver Municipal Code 17.08.090 says work regulated by the code may not start until the permit has been obtained, so permit review runs alongside ordering, not alongside demolition. A cosmetic refresh may need no building permit at all. Our page on whether a kitchen remodel needs a permit covers the rules for the city, the county and nearby towns.
Step 4: The pre-construction meeting
Before work starts, JDI holds a pre-construction meeting to go over logistics and expectations: working hours, where materials will be staged, how the rest of the house will be protected, and what you need to clear out of the kitchen. The design team hands the project to the construction crew, and a dedicated project manager becomes your main point of contact. From here you can follow the project in the client portal, which shows progress photos, daily reports and invoices.
Step 5: Construction, in order
The construction phase follows the same order whatever the level. A refresh skips several steps, which is why it is the shortest.
- Protection and demolition. Floors and doorways are protected, then the old cabinets, countertops and finishes come out. In a home built before 1978, painted surfaces that will be disturbed are handled under Washington's lead-safe renovation rules; see lead paint rules.
- Rough-ins. Plumbing, electrical and any ventilation or gas work for the new layout. This is the step that grows most in a full gut.
- Inspections. JDI schedules the city or county inspections. Walls are not closed until rough-in inspections pass. Our page on kitchen remodel inspections explains each one.
- Walls, ceiling and flooring. Drywall, patching and, depending on the plan, flooring before or after the cabinets.
- Cabinets. Set, leveled and fastened.
- Countertops. Stone and quartz tops are measured from the installed cabinets, fabricated, then installed. This gap is often the longest wait inside the construction phase.
- Finishes. Backsplash, sink and faucet, appliances, lighting, hardware and paint.
- Final inspection and punch list. The last inspections, then a list of small corrections worked through before closeout.
The kitchen is out of service from demolition until the countertops, sink and appliances are back in. Our page on living through a kitchen remodel covers setting up a temporary kitchen.
Step 6: The final walkthrough
When the work is done, you walk the kitchen with JDI to make sure everything meets your expectations. You receive documentation of the installed products, vendor warranties and product packets, along with JDI's 5-year written workmanship warranty. Keep these together; they are what you will need if anything needs attention later. Our page on kitchen remodel warranties explains how workmanship and product warranties differ.
What moves a schedule, and how to keep yours
- Late selection changes. Changing a cabinet or countertop after ordering resets that item's lead time.
- Backorders. A special-order item that slips can hold up the trades behind it.
- Hidden conditions. Rot under a sink, old wiring, or past work done without permits can turn up at demolition. These are most common in older homes and in full guts.
- Inspection corrections. A correction has to be made and re-inspected before work continues.
The protection you control most is simple: finish your selections before demolition, and answer questions from your project manager quickly while work is under way.
Getting your own dates
The figures on this page are typical, not a promise for your house. After the consultation and design, JDI gives you a schedule based on your scope, your selections and current lead times. To start, see how we handle kitchen remodeling in Vancouver, read the overview of our process, or schedule a free consultation.
Common questions
Does the 5 to 8 weeks for a full gut include design and permits?
No. Those figures cover the construction work in your kitchen. Design, selections, ordering and permit review happen before demolition, and how long they take depends on how quickly decisions are made, on product lead times and on the permit office. Your project manager gives you the construction dates once materials and the permit are lined up.
Why does a full gut have a range instead of one number?
Because a full gut changes what is inside the walls. Moving plumbing, adding circuits or opening a wall adds rough-in work and inspections, and the inspections have to pass before the walls are closed. Older homes can also reveal damage or past unpermitted work once the room is opened up. The more of that a project has, the closer it runs to the long end.
Who is my main contact once construction starts?
A dedicated project manager. At the pre-construction meeting the design team hands the project over to the construction side, and from then on the project manager is your point of contact. Progress photos, daily reports and invoices are posted to the client portal.
Can I stay in the house during a JDI kitchen remodel?
Most homeowners do. The kitchen is out of service from demolition until the countertops, sink and appliances are back in, so plan a temporary kitchen for that stretch. Our page on living through a kitchen remodel covers how to set one up.
What would make my project take longer than these figures?
The usual causes are a late change to a selection, a backordered item, a failed inspection that has to be corrected and re-inspected, and hidden conditions found during demolition, such as rot, old wiring or materials that need lead or asbestos handling. Most of these are avoided by finishing selections before demolition.
- Vancouver Municipal Code 17.08.090: permits required and exempt work
- City of Vancouver: Schedule a building inspection
Checked October 2026. Rules, fees and programs change; confirm the current requirement with the agency before you rely on it.
What kitchen clients say
This is our second time working with JDI... they do exceptional work and even more they stand begind the work they do which is getting rare these days. Looking forward to doing a Kitchen Remodel with them next, thanks again!
Anthony G. · Google review, May 13, 2026
JDI did a great job remodeling our rental house that needed a lot of work. They put in new floors, completely redid the kitchen and bathrooms. They also painted the entire interior. We had great communication and everything turned out fantastic.
Todd W. · Google review, Mar 15, 2026
The shower is stunning. I feel like I am in a spa. The new countertops and backsplash in the kitchen are beautiful. Art was great at keeping me informed every step of the project. The crew was so hard working and each was a perfectionist in what they did.
Virgil G. · Google review, Jan 7, 2026
Keep going
- JDI ConstructionOur remodeling processHow a JDI project runs from first call to final walkthrough.
- Planning · Budget and timingHow Long Does a Kitchen Remodel Take?The phases of a kitchen remodel in order, from design and permits to punch list, what each one waits on, and what stretches a schedule in Vancouver, WA.
- Exploring · Plan your kitchenRefresh, Pull-and-Replace or Full Gut: Kitchen Remodel Levels ExplainedFour kitchen remodel levels compared for Vancouver, WA homes: what each includes, what triggers a permit, how the cost relates and who each one suits.
- JDI ConstructionRequest a free consultationAn in-home visit, an itemized plan and a 3D design layout.