Lead Paint Rules for Kitchen Remodels in Pre-1978 Homes
By the JDI Construction teamReviewed by Arthur Kulchitskiy, CEOUpdated October 20265 min read
In Washington, paid renovation work that disturbs paint in a pre-1978 home must be done by a certified firm using certified renovators (WAC 365-230-330). The Department of Commerce runs the program, not the EPA. The firm must give you the Renovate Right pamphlet no more than 60 days before work begins and contain dust inside the work area.
If your home was built before 1978, a kitchen remodel will probably disturb painted surfaces that could contain lead: walls behind cabinets, soffits, window and door trim, and sometimes the old cabinets themselves. Sanding, cutting and demolition turn that paint into dust. Washington regulates how paid contractors handle it. This page covers the rules as of October 2026 and what they mean on a real job.
Which rule applies in Washington
The national standard is the EPA's Renovation, Repair and Painting (RRP) rule. In Washington it is administered by the state. The Department of Commerce Lead-Based Paint Program provides "training, certification and compliance enforcement" under chapter 70A.420 RCW and chapter 365-230 WAC.
WAC 365-230-300 applies the state rules "to all renovations performed for compensation in target housing and child-occupied facilities". Commerce describes who needs certification in practical terms: any firm or individual that will "Offer, bid, or contract to work on pre-1978 properties", for work including "Home renovations", "Remodels", "Painting" and "Any work that disturbs paint in a pre-1978 property".
The core requirement is in WAC 365-230-330(1): "Renovations must be performed by certified firms using certified renovators".
When the rule does and does not apply
| Situation | Do the certified-firm rules apply? | Basis |
|---|---|---|
| A contractor remodels a kitchen in a pre-1978 home | Yes | WAC 365-230-300, 365-230-330 |
| The affected components have been tested and found free of lead-based paint by a certified inspector, or by a certified renovator using a recognized test kit or lab sample | No, for those components | WAC 365-230-300 |
| Minor repair disturbing six square feet or less of painted surface per room, with no window replacement or demolition of painted surfaces | No | WAC 365-230-310 |
| You do the work yourself in the home you own and live in | Generally no | WAC 365-230-300; EPA guidance |
| You do the work yourself but rent out all or part of the home, run a childcare center in it, or renovate to sell for profit | Yes, according to EPA | EPA guidance |
The small-job exclusion is narrower than it looks. The six-square-foot limit is per room, the exterior limit is twenty square feet, and the exclusion disappears if the work involves window replacement, demolition of painted surface areas, or prohibited practices. Pulling a wall of cabinets and the soffit above them is demolition, not minor repair.
What a certified firm does differently
Lead-safe work is mostly about keeping dust where it is made. WAC 365-230-330(1)(a) and (b) describe what you should expect to see on a job in a pre-1978 kitchen:
- Warning signs that define the work area.
- Containment set up so that "no dust or debris leaves the work area".
- Floors covered with taped-down plastic "six feet beyond the perimeter of surfaces undergoing renovation".
- Ducts, windows and doors in the work area closed and covered.
On a kitchen that usually means the room is sealed off from the rest of the house during demolition, heating and cooling registers are covered, and the household uses a different route in and out. Those measures overlap with ordinary dust control, which is one reason a temporary kitchen should be set up outside the plastic. Practical planning for that period is in living through a kitchen remodel.
The pamphlet you should receive
WAC 365-230-320(1) sets the timing: "No more than sixty days before beginning renovation activities in any residential dwelling unit of target housing, the firm performing the renovation must" provide the owner with the pamphlet. The firm must then either obtain your written acknowledgment that you received it, or obtain a certificate of mailing at least seven days before the renovation.
The pamphlet is a specific document. WAC 365-230-310 defines it as "the EPA pamphlet titled 'The Lead-Safe Certified Guide to Renovate Right'". If you are asked to sign an acknowledgment, you should have the pamphlet in hand when you sign.
This is separate from the contractor disclosure every Washington homeowner receives on jobs of $1,000 or more. That notice is explained in contracts, deposits and change orders.
How to check a firm's certification
- Ask for the certificate. A certified firm holds a Department of Commerce certificate. Commerce says certificates "are valid up to 5 years", so check the expiration date.
- Look at Commerce's published lists. Its Business and Homeowner Resources page offers downloadable spreadsheets: "Certified RRP Companies - Alphabetical List" and "Certified RRP Companies - by City and County".
- Check the enforcement records. The same page links "Enforcement Action Records" and "Suspended and Revoked/Denied Companies".
- Contact Commerce with questions: LBPInfo@Commerce.wa.gov or 360-586-5323.
Lead certification is a different credential from contractor registration. Both should check out. The registration lookup is covered in how to verify a contractor in Washington.
If you are doing the work yourself
The state rule covers renovations "performed for compensation", and the EPA says: "In general, the RRP Rule does not apply to homeowners doing RRP projects in their own pre-1978 homes." The EPA adds that it does apply "if you rent all or part of your home, operate a childcare center in your home or if you buy, renovate and sell homes for profit".
Being outside the rule does not make the dust any safer. The work practices certified firms are required to use (containment, covered floors, closed and covered ducts and openings) are the reasonable model for a homeowner too, and the Renovate Right pamphlet is free to read before you start. If any part of your kitchen project is hired out, the rule applies to the firm you pay for that part. What else an owner may and may not do is in DIY kitchen remodeling in Washington.
Lead and asbestos are separate questions
Older kitchens raise both, and the rules, agencies and people involved are different. Lead is a Department of Commerce program focused on paint. Asbestos in Clark County is regulated by the Southwest Clean Air Agency and L&I and concerns materials such as old sheet flooring and its adhesive. A lead-safe certificate does not cover asbestos work. See asbestos and kitchen remodels in Clark County.
Where JDI fits
If your home predates 1978, tell any contractor you interview at the first conversation and ask to see its Commerce certificate. That includes us. JDI Construction offers a free in-home consultation, and you can start on our Vancouver kitchen remodeling page.
Common questions
Can a contractor test instead of assuming there is lead paint?
Yes. WAC 365-230-300 excepts renovations where a certified inspector, or a certified renovator using a recognized test kit or a lab sample, has determined that the affected components are free of lead-based paint. The finding applies to the components that were tested, so it should be documented and specific to the surfaces your kitchen remodel will disturb.
How long does a lead-safe renovation certificate last?
The Department of Commerce says RRP certificates are valid up to 5 years. When you ask a firm for its certificate, look at the expiration date as well as the name on it, and check that the name matches the business on your contract.
Is the EPA or Washington State in charge of lead renovation rules here?
Washington. The Department of Commerce Lead-Based Paint Program handles training, certification and enforcement under chapter 70A.420 RCW and chapter 365-230 WAC. EPA's firm certification page lists Washington among the states authorized to run their own program, although another EPA page omits it from a similar list, so direct certification questions to Commerce.
Does the rule apply if only a small patch of wall is disturbed?
Possibly not. WAC 365-230-310 excludes minor repair and maintenance that disrupts six square feet or less of painted surface per room indoors, provided no prohibited practices are used and the work does not involve window replacement or demolition of painted surface areas. A kitchen remodel that removes cabinets, soffits or wall sections will usually go beyond that.
Who do I contact with a question about a firm's lead certification?
The Department of Commerce Lead-Based Paint Program, at LBPInfo@Commerce.wa.gov or 360-586-5323. Commerce also publishes enforcement action records and a list of suspended, revoked or denied companies on its Business and Homeowner Resources page.
- Washington Department of Commerce: Lead-Based Paint Program
- Commerce: Business and Homeowner Resources (certified firm lists)
- WAC 365-230-300: Scope of renovation rules
- WAC 365-230-310: Definitions (pamphlet, minor repair)
- WAC 365-230-320: Information distribution requirements
- WAC 365-230-330: Work practice standards
- EPA: Lead Renovation, Repair and Painting Program
- U.S. Census Bureau: ACS 2020-2024 table DP04, Vancouver city
Checked October 2026. Rules, fees and programs change; confirm the current requirement with the agency before you rely on it.
This page is general information for homeowners, not legal advice. For a decision about your own contract, lien or dispute, talk to a Washington attorney.
Keep going
- Exploring · Plan your kitchenKitchen Remodeling by Home Era in Vancouver, WAWhat kitchens in Vancouver, WA homes of each era tend to need, from pre-war houses near downtown to newer construction, with lead and asbestos cautions.
- Planning · Budget and timingLiving Through a Kitchen Remodel: Temporary Kitchens and Dust ControlHow to live at home during a kitchen remodel: setting up a temporary kitchen, dust control, protecting floors, pets and children, and lead-safe work.
- JDI ConstructionKitchen remodeling in Vancouver, WAOur kitchen remodeling service, recent projects and what to expect.
- Planning · Washington law and your protectionsAsbestos and Kitchen Remodels in Clark CountyAsbestos rules for kitchen remodels in Clark County: the Southwest Clean Air Agency survey requirement, who may inspect and remove it, and the 10-day notice.