How Long Does a Kitchen Remodel Take?
By the JDI Construction teamReviewed by Arthur Kulchitskiy, CEOUpdated October 20266 min read
On average, a kitchen remodel takes longer to plan than to build. In the 2026 U.S. Houzz and Home Study, homeowners reported an average of 9.5 months planning and 5.8 months of construction for kitchen projects nationally. Your own schedule depends on design decisions, cabinet lead time, permit review and inspections. Ask your contractor for a written schedule based on current lead times.
The honest answer is that it depends on your kitchen, and that most of the time is spent before anyone picks up a tool. This page does not give a number of weeks for each phase, because no reliable published figure exists for cabinet or countertop lead times and every project differs. It sets out the sequence, explains what each phase is waiting on, and gives the few durations that official sources do publish.
One national benchmark
In the 2026 U.S. Houzz & Home Study, as reported by Houzz Pro on April 27, 2026, "Kitchen projects have the longest timeline overall on average: 9.5 months spent on planning and 5.8 months spent on construction." Those are averages reported by renovating homeowners across the country for projects done in 2025. They cover every size of kitchen project and include the time owners spent thinking, saving and choosing before they hired anyone.
Treat that as context, not a prediction. The useful point is the proportion: planning took longer than building.
The phases in order
| Phase | What happens | What it waits on |
|---|---|---|
| 1. Consultation and design | Site measure, layout, drawings, scope | Your decisions on layout and budget |
| 2. Selections | Cabinets, counters, flooring, fixtures, appliances, lighting chosen | Your choices, and product availability |
| 3. Ordering | Cabinets and other long-lead items ordered | Final drawings and signed selections |
| 4. Permits | Application, plan review, permit issued | Complete drawings, and the permit office |
| 5. Site preparation and demolition | Protection, containment, removal of the old kitchen | Permit, materials testing, cabinet delivery date |
| 6. Framing and rough-ins | Any wall changes, then plumbing, gas, ducting and wiring in open walls | Demolition, and any structural details |
| 7. Rough inspections | Inspectors check the work before it is covered | Inspection scheduling, and passing |
| 8. Insulation and drywall | Walls closed, taped, finished, primed | Approved rough inspections |
| 9. Flooring and cabinets | Flooring where it runs under cabinets, then cabinet installation | Cabinet delivery |
| 10. Countertop template and install | Tops measured from the installed cabinets, fabricated, then set | Cabinets fixed in place, then fabrication |
| 11. Finishes | Backsplash, plumbing fixtures, appliances, lighting, trim, paint | Countertops |
| 12. Final inspections and punch list | Final sign-offs, walkthrough, corrections | All work complete |
For a fuller description of each step, see the article on the steps in a kitchen remodel.
Before construction: design, selections and ordering
This is the part you control, and it is where schedules are won or lost. The design fixes the cabinet layout. The cabinet order cannot be placed until the layout and the appliance models are final, because cabinets are built around appliance dimensions. Everything downstream waits for the cabinets.
No trustworthy industry statistic for cabinet or countertop lead times was found for this guide. They vary by manufacturer and season. Ask your contractor for the lead time they are being quoted today for the cabinet line you have chosen, and ask what it would be for an alternative. The cabinet guide explains why custom work generally takes longer than stock.
Permits
If the remodel needs a building permit, the permit sits between design and demolition. Not every kitchen needs one. See whether you need a permit.
Outside the city limits the permit office is different, and electrical permits come from the Washington Department of Labor & Industries, which says its online permits are processed immediately. Clark County publishes its average permit processing times on its Permit Center page. Check the office for your address and ask your contractor what they are seeing currently.
Demolition and what has to happen first
Demolition is quick. What comes before it is not always.
- Asbestos. In Clark County, the Southwest Clean Air Agency requires the owner or the owner's agent to determine whether suspect asbestos-containing materials are in the work area before any renovation. If asbestos has to be removed, the agency's rule sets a notification period of 10 days after a complete notice is submitted, and the removal may begin the day after that period. See asbestos and kitchen remodels.
- Lead. In a home built before 1978, a certified firm must give you the lead hazard pamphlet before starting, and set up containment. See lead paint rules.
- Timing against the cabinets. Many contractors schedule demolition so that the rough-in work finishes close to the cabinet delivery date. Starting demolition long before the cabinets exist means living without a kitchen for longer than necessary.
Rough-ins and inspections
With the walls open, the trades run new plumbing, gas piping, ductwork and wiring. Then the work stops until it is inspected. Vancouver Municipal Code 17.08.140 requires that work "remain accessible and exposed for inspection purposes until approved," and that the framing inspection happens after the rough electrical, plumbing and mechanical work has been inspected and approved. Drywall cannot go up until then.
The city says inspection requests received after 7 a.m. are inspected the next business day and that inspections may be scheduled up to five days in advance. The code also lets the building official require inspections to be scheduled at least three working days ahead, so a next-day visit should not be assumed. A failed inspection means a correction and a reinspection before the next trade can start. The sequence is described in kitchen remodel inspections.
Cabinets, countertops and the gap between them
Once drywall is finished, cabinets go in. Countertops made of stone, quartz or solid surface are then measured from the installed cabinets, not from the drawings, because the tops have to fit the walls and boxes as built. Fabrication follows the template, and installation follows fabrication.
That gap is built into every kitchen with fabricated tops, and it is the stretch owners find hardest: the kitchen looks nearly done but has no sink. Ask your fabricator's current turnaround from template to install, and whether a temporary sink or top can be set in the meantime. Backsplash, plumbing fixtures and most appliances wait for the countertops.
What extends a schedule
- Late or changed selections. A change after ordering can restart a lead time.
- Change orders. Added work adds time as well as cost, and changes that depart from the approved plans have to be resubmitted to the city as amended construction documents.
- Hidden conditions. Damaged subfloor, old wiring or earlier unpermitted work found at demolition.
- Layout changes. Moving plumbing or opening a wall adds rough-in work, inspections and sometimes engineering.
- Damaged or wrong deliveries. One missing cabinet can hold up the countertop template.
- Incomplete permit submittals and failed inspections.
- Historic review. A home on the Clark County Heritage Register needs a certificate of appropriateness before a permit is issued if the work affects features listed in its designation.
- Financing and decisions by owners that are not ready when the contractor is.
Getting a schedule you can rely on
Ask for a written schedule that shows the order of work, the dates that depend on deliveries and the points where you need to make a decision. Ask how you will be told when something moves. JDI Construction handles permits and project management for its clients and posts updates through a client portal, and the stages are described on the our process page. While the work is under way, living through a kitchen remodel covers the practical side, and kitchen remodeling in Vancouver explains how to start.
Common questions
Can demolition start while the permit is still in review?
Not for work that needs the permit. Vancouver Municipal Code 17.08.090 says no work regulated by the code may be done unless a permit has first been obtained, and work started early is subject to an investigation fee equal to the permit fee. Use the review period for selections and ordering instead.
How long is a City of Vancouver remodel permit good for?
Under Vancouver Municipal Code 17.08.110, work must begin within 180 days of the permit being issued, and a residential building permit expires two years from the date of issuance. The building official may grant one extension of up to 180 days. An application that has not resulted in an issued permit within one year of filing expires.
Will my kitchen be unusable for the whole construction period?
For most of it, yes. The kitchen goes out of service at demolition and is not fully usable until the countertops, sink and appliances are in. That is why the countertop step matters so much to the schedule, and why a temporary kitchen is worth setting up properly.
Do building code changes affect when I should start?
They can affect which rules apply. The Washington State Building Code Council states that the 2024 codes take effect May 3, 2027, and the Department of Labor and Industries adopts the 2026 National Electrical Code effective December 31, 2026, applied by electrical permit issue date. The City of Vancouver runs its own electrical permits, so confirm its date with the Permit Center. If your permit will be issued near either date, ask your contractor which edition your project falls under.
Is winter a bad time to remodel a kitchen?
A kitchen remodel is mostly interior work, so the season matters less than it does for exterior projects. It matters when the scope includes a new window, an exterior door or a hood duct through an outside wall. What affects the schedule more is how early the design and orders are finished.
- Houzz Pro: 2026 U.S. Houzz and Home Study findings (27 April 2026)
- City of Vancouver: Residential building permits
- City of Vancouver: ePlans
- Vancouver Municipal Code 17.08.110: Permit issuance and expiration
- Vancouver Municipal Code 17.08.140: Inspections
- City of Vancouver: Schedule a building inspection
- Southwest Clean Air Agency: SWCAA 476, Standards for Asbestos Control, Demolition and Renovation
- Washington State Building Code Council
Checked October 2026. Rules, fees and programs change; confirm the current requirement with the agency before you rely on it.
Keep going
- JDI ConstructionOur remodeling processHow a JDI project runs from first call to final walkthrough.
- JDI ConstructionKitchen remodeling in Vancouver, WAOur kitchen remodeling service, recent projects and what to expect.
- Planning · Budget and timingLiving Through a Kitchen Remodel: Temporary Kitchens and Dust ControlHow to live at home during a kitchen remodel: setting up a temporary kitchen, dust control, protecting floors, pets and children, and lead-safe work.
- Planning · Budget and timingKitchen Remodel Cost in Vancouver, WAJDI Construction's published planning ranges for a kitchen remodel in Vancouver, WA by kitchen size and finish tier, plus add-on ranges and sales tax.