Washington Construction Liens: What Homeowners Should Know

By the JDI Construction teamReviewed by Arthur Kulchitskiy, CEOUpdated October 20266 min read

Quick answer

Under RCW 60.04.021, anyone who furnishes labor, materials, equipment or professional services for your remodel can claim a lien on your home if they are not paid, even if you paid your contractor. A lien must be recorded within 90 days after the claimant last furnished work or materials (RCW 60.04.091) and expires eight months after recording unless a lawsuit is filed (RCW 60.04.141).

A construction lien is a claim recorded against your property by someone who says they were not paid for work or materials that went into it. The uncomfortable part for homeowners is that the unpaid party does not have to be someone you hired. This page explains how liens work under chapter 60.04 RCW as of October 2026 and the protections the Department of Labor & Industries (L&I) describes.

Who can lien your home

RCW 60.04.021 gives a lien to "any person furnishing labor, professional services, materials, or equipment for the improvement of real property", for the contract price of what they furnished at the request of the owner or the owner's agent. Your contractor is treated as your agent for this purpose.

On a kitchen remodel that list can include the general contractor, the electrician and plumber working under it, the cabinet supplier, the countertop fabricator, the lumberyard, and individual workers. L&I puts the consequence plainly: if your contractor does not pay subcontractors, suppliers or laborers, "those who are owed money can look to your property for payment, even if you have paid your contractor in full."

The notices you may receive

Washington uses written notice to warn owners before a lien is possible. Who has to send one depends on their relationship to you.

WhoMust they send you a notice first?Section
A contractor you hired directlyNo. On a remodel of an owner-occupied single-family home, it has a lien for the full amount dueRCW 60.04.031(3)(a)
A supplier of materials, equipment or professional services that did not contract with youYes. A written "notice of the right to claim a lien"RCW 60.04.031(1), (3)(b)
A laborer whose claim is based only on performing laborNoRCW 60.04.031(2)

The statutory form is titled "NOTICE TO OWNER" with the line "PROTECT YOURSELF FROM PAYING TWICE", and it states "THIS IS NOT A LIEN". Receiving one is normal on a well-run job. It means a supplier is following the law, not that your contractor has failed to pay.

Separately, your contractor must give you two documents before work starts on a residential job of $1,000 or more: the Notice to Customer disclosure and L&I's lien information sheet (RCW 18.27.114 and RCW 60.04.255(2)). The disclosure is described in contracts, deposits and change orders.

The limit that protects owner-occupied remodels

Washington gives people remodeling the home they live in a protection that other owners do not have. Under RCW 60.04.031(3)(b), on the remodel of an existing owner-occupied single-family residence, the liens of those who did not contract directly with you "may only be satisfied from amounts not yet paid to the prime contractor by the owner at the time the notice described in this section is received".

In plain terms: money you had already paid your contractor before a supplier's notice reached you is not exposed to that supplier's lien. Money you still hold is.

Three details matter:

  • The clock runs from receipt of the notice. "Received" means actual receipt by personal service or registered or certified mail, or three days after mailing by registered or certified mail, not counting Saturdays, Sundays or legal holidays.
  • It applies only to an owner-occupied single-family residence. A rental or a house you are fixing up to sell is outside it.
  • It does not limit the party you hired. Your own contractor's lien rights for unpaid amounts are not reduced by this rule.

Deadlines and how long a lien lasts

StepDeadlineSection
Claimant records the claim of lien"Not later than ninety days after the person has ceased to furnish labor, professional services, materials, or equipment"RCW 60.04.091
Claimant gives the owner a copyBy certified or registered mail or personal service "within fourteen days of the time the claim of lien is filed for recording". Missing it forfeits the claimant's right to attorneys' fees and costs against the ownerRCW 60.04.091
Lien expires unless a lawsuit is filed"Eight calendar months after the claim of lien has been recorded"RCW 60.04.141
Owner must be served with that lawsuit"Within ninety days of the date of filing the action"RCW 60.04.141
Court may dismiss a stalled caseIf not prosecuted to judgment within two yearsRCW 60.04.141

The practical reading: a lien can appear up to about three months after the last delivery or day of work on your kitchen, which may be after you have made final payment. That is why the releases below are collected before the last check, not after.

Lien releases and the protections L&I describes

RCW 60.04.071 says that once a lien claimant has been paid and the owner asks, the claimant "shall immediately prepare and execute a release of all lien rights for which payment has been made". L&I's lien fact sheet builds its advice around that right:

  • Lien releases. "Before making final payment on the project, request a completed lien release form from each contractor and material supplier." L&I publishes a sample Waiver of Lien, form F625-029-000.
  • Joint checks. "Make your checks payable jointly to both the contractor and the subcontractor or supplier as payees." The statutory notice calls these dual paychecks.
  • Disclosure of who could lien. "Ask the prime contractor to disclose all potential lien claimants as a condition of payment."
  • Holding back. "For greater protection, you may withhold a percentage of your contract until you are satisfied with the project." This has to be written into the contract.
  • A performance bond or escrow. L&I suggests asking the contractor to post a performance bond in the amount of the project cost, or using an escrow agent.

Most of these work only if they are agreed before the job starts, so raise them when you are comparing bids. They fit naturally into the questions to ask a kitchen contractor.

If you receive a notice or a lien

The options below are the ones the statutes and L&I describe. They are general information; which fits your situation is a question for an attorney.

  • After a notice of intent to lien: L&I says to tell your contractor, ask for the lien release from that supplier or subcontractor, and "Do not make further payments to your contractor until this is satisfied."
  • Withholding during a lien action: under RCW 60.04.151, while a lien action is pending the owner "may withhold from the prime contractor the amount of money for which a claim is recorded by any subcontractor, supplier, or laborer".
  • Challenging a lien: under RCW 60.04.081, an owner who believes a lien is "frivolous and made without reasonable cause, or clearly excessive" may ask the superior court for a hearing, held 6 to 15 days after service. The side that prevails recovers costs and attorneys' fees, so this route cuts both ways.
  • Bonding around it: RCW 60.04.161 lets an owner record a surety bond to free the property while the dispute continues.

In a lien foreclosure action the court may also order the losing side to pay the prevailing party's attorneys' fees and costs (RCW 60.04.181(3)). Broader dispute routes, including claims against a contractor's bond, are in if a remodel goes wrong.

Reducing lien risk before you hire

Lien problems usually trace back to a contractor that is not paying its bills. Checking the business first is the cheapest protection. L&I's Verify tool shows lawsuits against a contractor's bond and how long it has been registered; see how to verify a contractor in Washington. An unregistered contractor leaves you with the lien exposure and no bond behind it.

JDI Construction runs design and construction as one accountable team and manages the project for the homeowner. If you would like to talk through how payments and releases are handled on our projects, see our Vancouver kitchen remodeling page.

Common questions

Is a 'Notice to Owner' a lien on my house?

No. The statutory form in RCW 60.04.031(4) is headed 'NOTICE TO OWNER' and states 'THIS IS NOT A LIEN'. It tells you that a supplier or other party is working on your project and could claim a lien later if unpaid. It is also the document that fixes how much that party could collect from an owner-occupied remodel, so note the date you received it.

Can I remove a lien from my title without paying the claimant?

RCW 60.04.161 lets an owner record a surety bond that releases the property from the lien. The bond must be the greater of five thousand dollars or two times the lien if the lien is ten thousand dollars or less, and one and one-half times the lien if it exceeds ten thousand dollars. The dispute then continues against the bond instead of the house.

Will my lender tell me about liens?

RCW 60.04.255(1) requires lenders to give L&I's lien information material to anyone borrowing for residential construction, repair or remodeling. Your contractor must give you the same sheet. The current version is L&I's 'Facts About Construction Liens', publication F625-017-000, dated 01-2026.

Can a contractor who skipped the required paperwork still lien my home?

Two rules limit that. RCW 18.27.114(4) says a contractor that did not give the required Notice to Customer disclosure cannot bring or maintain a lien claim on that contract. RCW 60.04.031(6) says a lien cannot be enforced unless the claimant complied with the notice provisions that applied to it.